Change to major highway exit plans

Plans for the second temporary closure of the Bruce Highway’s northbound Dohles Rocks Rd exit have changed.

Due to forecast weather conditions and its potential impact on construction, this weekend's closure of the Dohles Rocks Rd exit ramp (Exit 130) has been postponed.

The revised closure dates are now Friday August 14 to Monday August 17 and if required Friday August 21 to Monday August 24.

Temporary closures on this section of the $2 billion Bruce Highway upgrade, will be from 10pm on the Friday to 4am the Monday.

Detour signage will be in place to help motorists who will need to:

  • use the Anzac Avenue exit (Exit 133) during the closure periods

  • follow the signed detour route

  • allow additional travel time.

Some of the construction activities on the ramp are dependent on suitable weather conditions, particularly earthworks, drainage installation, and road pavement works.

Wet weather can make these activities unsafe for workers, increase risks for motorists travelling near the work area, and affect the quality of the finished work.

If the works cannot be completed as planned, the closure dates may be revised.

Transport and Main Roads (TMR) says residents and motorists will be notified in advance of any further changes or additional closures.

TMR thanks motorists and residents for their patience and understanding during these road works.