Bruce Highway upgrade update ahead of Christmas
Published 3:03pm 10 December 2025
Words by Kylie Knight
Transport and Main Roads has provided an update on the Bruce Highway upgrade from Dohles Rocks Rd to Anzac Ave and details of what to expect during the peak Christmas period.
In its December Project Update, TMR says stage one of the project is “progressing well” since kicking off in April this year.
What the construction team has been achieved so far ...
• moved 5400 trucks of dirt from the centre median and started installing the pavement to widen the centre median
• installed 98 noise barrier poles in preparation for new and upgraded noise barriers either side of the Bruce Highway
• drilled 182 bored piles as foundations for the new noise barriers. Bored piles are deep holes drilled and filled with concrete to create strong foundations for heavy structures
• moved 12 electricity power poles to allow space for the two new ramps, including the cables over the Bruce Highway
• installed 121 temporary caution signs while the project is ongoing, as well as 5.5km of concrete barriers
• dug 535m of underground tunnels for drainage, sewer and water
• delivered 25,000 tonnes of rock to site to strengthen the ground for the new ramps.
From Saturday, December 20 to Monday, January 5, construction will temporarily stop for the holiday period. The 80 km/h speed limit on the highway will remain in placed due to changed traffic conditions.
In early 2026, the team will ...
• complete earthworks and commence pavement works on the southbound exit ramp
• complete retaining wall works on the northbound entry ramp
• finalise water and sewer connections
• start to construct the noise barriers on the eastern side of the highway
• install road lighting in the centre median.
To find out more, speak to the project team at Murrumba Downs Shopping Centre, outside Coles, on Thursday, December 11 from 3-6pm.
Residents can also phone 1800 749 022 or email [email protected]
Related Stories
Police launch Christmas toy drive
Hooning crackdown sees 244 charged
Boaties urged to prepare now
Top Stories
Boaties urged to prepare now
Maritime Safety Queensland is urging Moreton Bay boaties to prepare for severe weather by checking moorings, safety equipment and vessel plans ahead of storms and flooding.
Family fights for Carol's Law
A Moreton Bay family is campaigning for Carol's Law, calling for mandatory driver vision testing in Queensland after losing a loved one in a cycling tragedy.
Success, the Redcliffe way
Redcliffe State High School celebrates student achievements in academics, sport and leadership, highlighting the friendships, teachers and opportunities behind their success.
Work starts on Mango Hill hotel
Construction has begun on a new 112-room hotel and leisure precinct in Mango Hill, featuring a luxury bathhouse and proposed golf driving range, with opening planned for late 2028.
Santa's got mail
Australia Post's Santa Mail is back for Christmas 2026, inviting Moreton Bay children to send letters to Santa by December 20 and receive a special reply and festive ornament.
Popular Stories
Drivers switch off safety tech
RACQ research reveals Queensland motorists are switching off potentially life-saving car safety features, raising concerns about road safety as the state's road toll climbs.
Opportunity through connection
Tribe Social Belonging is tackling social isolation across Moreton Bay through inclusive community spaces, driver mentoring and support programs that help locals connect and thrive.
Mick Hanfling Park upgrades progress
Final upgrades at Mick Hanfling Park, Lake Kurwongbah, are underway, with new amenities, accessible pathways and kayak facilities expected by December 10.