Contractor anchored for dam work
Published 5:03am 2 June 2025
Words by Nick Crockford
A major upgrade to North Pine Dam will start this year after Seqwater awarded the contract for initial strengthening works.
SRG Global Civil will deliver the works from mid-2025 (finishing in 2027) at the start of improvements costing more than $69 million.
Stage one includes installing more than 50 post-tensioned anchors into the monoliths which form part of the dam wall, ranging from 42-102 metres in length.
The anchors will add around 75,000 tonnes of effective weight into the dam wall to further strengthen the structure. Work will support approximately 50 jobs on-site.
Seqwater Executive General Manager Infrastructure, Planning and Capital Delivery, Sarah Dixon, said strengthening will prepare the dam for majors works.
“North Pine Dam plays an important role in the SEQ Water Grid and supplies drinking water for the people of north Brisbane and Moreton Bay,” said Ms Dixon.
While North Pine Dam continues to operate safely under normal conditions, North Pine Dam Improvement Project will ensure it meets modern engineering and design standards.
“The strengthening works starting this year will deliver enhanced safety benefits and prepare the dam for its major upgrade in the future.”
A Detailed Business Case is underway for the North Pine Dam Improvement Project to inform the design of the planned upgrade - the first major upgrade since the dam's construction in 1976.
Seqwater will be hosting regular community information sessions to provide further details. To stay up to date, visit the Seqwater website.
To connect with the project team, email [email protected] or call 07 3432 7000 during business hours.
Related Stories
New memorial honours Redcliffe veterans
Christmas wishes for Redcliffe Hospital
Making sport accessible to all
Top Stories
Making sport accessible to all
Sport4All inclusion coach Emily Finn-Brumm has worked with 181 Moreton Bay organisations to make sport and recreation more accessible for people with disability.
Big top returns to Deception Bay
Ashton's The Great Australian Circus returns to Deception Bay after 20 years, bringing thrilling acrobatics, aerial acts and motorbike stunts from November 13-29.
One minute to remember
RSL Queensland is encouraging Moreton Bay residents to observe a minute's silence at 11am on November 11 to honour those who served and sacrificed their lives.
Siblings reel in double victory
Burpengary East siblings Alexis and Hunter Pittman have both claimed first place in their age groups at the Aussie Junior Fishing Classic, celebrating a double fishing victory.
$81 million Caboolture road upgrade advances
The $81 million Caboolture River Road upgrade in Morayfield is moving forward, with plans to widen the road to four lanes and begin construction in 2027.
Popular Stories
Monopoly reveals first Moreton Bay property
Lake Samsonvale has been revealed as a landmark on the new Monopoly: Moreton Bay Edition board, ahead of its official launch at Redcliffe Jetty on November 4.
Sand boost for Woorim Beach
Woorim Beach on Bribie Island is receiving 175,000 cubic metres of sand to repair erosion damage, restore dunes and strengthen coastal protection ahead of storm season.
Morayfield South prepares for 26,000 residents
Morayfield South's new structure plan paves the way for up to 26,000 residents, with future housing, roads, schools, parks and wildlife corridors.