Suttons Beach Pavilion demolition ramps up
Published 7:00am 13 March 2024
Words by Kylie Knight
Demolition of the Suttons Beach pavilion structures is in full swing, as the design competition to decide what will replace them ramps up.
The work, which started in December, was scheduled to take up to 15 weeks with a four-week allowance for wet weather possibly pushing it out to late May.
A tender of $1,937,451 was awarded to AllenCon Pty Ltd to complete the work.
A Moreton Bay City Council spokeswoman says: “During the demolition works, Council has been diligently working with our contractor to safely demolish the existing Suttons Beach Pavilion structures.
“Currently, the contractor is anchoring the retaining wall behind Pavilion One to maintain bank stability. Once the anchoring works are complete, the contractor will commence the demolition of Pavilion One. Removal of Pavilion One will also include the salvage of the red bricks where reasonable and feasible to do so.
“During the works, the contractor has also removed a secondary floor slab and material from under Pavilion Two and the existing retaining wall. The contractor has recently commenced construction of a new retaining wall at the site of Pavilion Two.”
Council has engaged CityLab to run a design competition to come up with a replacement building.
“We have invited architects via stage one to submit an expression of interest in the competition,” the spokeswoman says.
“The jury is reviewing those applications and we are hoping to advise and publish the shortlisted parties on our website in the coming weeks.
“In stage two of the competition, the shortlisted architects will further develop their designs which will then be reviewed by the appointed jury members, and the winning design will be announced and shared with the community in mid-2024.”
Council has secured $11.33 million in funding for the $19 million Suttons Beach Pavilion Development project through the SEQ City Deal Liveability Fund.
The fund aims to deliver ‘region-shaping legacy’ projects in the lead-up to the Brisbane 2032 Olympic and Paralympic Games.
Demolition photo gallery
By Dominika Lis
Related Stories
SOL Society launches with sold-out wellness rave
Work starts on new Kids Club
Pru calls time on clothing exchange
Top Stories
Pru calls time on clothing exchange
After nine years helping families access affordable clothing, Margate’s Blackbird Clothing Exchange is closing, with founder Pru Burke citing health reasons and thanking the community for its support.
Firing up for ‘large scale’ racing
Top drivers from across Australia will battle for state honours at the 2026 Large Scale Queensland Titles, bringing three days of high-speed RC racing to Brendale’s England Park Raceway.
Quantum leap for Moreton Bay
Work will officially start today on PsiQuantum’s new Moreton Bay Central facility where the world's first utility-scale, fault-tolerant quantum computer will be built.
MISA's mission to support Moreton Bay men
For Men’s Health Week, Strathpine-based MISA is encouraging men to prioritise mental health, offering specialised counselling and support for blokes of all ages.
Bluey to star at free family event
Bluey and Bingo are heading to Redcliffe for a free family event featuring live entertainment, activities, community services and fun for little Queenslanders.
Popular Stories
Great Mate plans to get bigger and better
The Great Mate Check-In’s flagship men’s mental health event raised more than $6,000 for counselling and community grants, with organisers promising an even bigger and better event next year.
Bridge plan seeks new approval
The proposed $750 million Bribie Island Bridge has entered the federal environmental approval process, with construction expected to begin in 2028 and deliver safer, improved traffic and active transport connections.
Aussie stars heading to Woodford
Australia’s top axemen are heading to Woodford Show for a rare national woodchop championship, alongside monster trucks, stunt shows, food challenges, fireworks and family entertainment.