The Redcliffe Jetty has been considered the heart of the Redcliffe peninsula ever since boats carrying holidaymakers started arriving in the late 1800s. In those days, Brisbane residents who wanted to visit the popular seaside resort either had to embark on a four-hour coach ride or a two to three-hour journey by sea.
1881 Reverend John Sutton and other landowners requested Assistant Marine Surveyor FDG Stanley to survey for a jetty at Redcliffe Point
1881 (May 19) The survey report was submitted to the Government. It suggested a jetty be built at Redcliffe Point - north of the reefs projecting from the point. The site had been used by steamers landing timber and was considered the most sheltered and accessible part of the coast. The estimated cost was £1050
1883 (July 18) The ratepayers of Humpybong signed a petition which was presented to the Caboolture Divisional Board. The Board decided to refer the subject to a special committee to further investigate the project. It was felt a Redcliffe Jetty was needed to stop residents having to travel to the Woody Point Jetty and to provide better deep water access to the peninsula.
1884 (July) The Caboolture Divisional Board invited tenders for the Redcliffe Jetty. No suitable tenders were received from outside companies, so the work was carried out by day labour. S Walters was appointed supervisor and was expected to take approximately three months
1884 (August 27) Work began on the Redcliffe jetty. Approximately 10,000 feet of timber was on site and ironwork was supplied by Messers JW Sutton and Co
1885 The Jetty Construction Committee of the Caboolture Divisional Board reported that the construction of the Redcliffe Jetty was finished. The final cost was £1357.5.2
1888 The Redcliffe Divisional Board was proclaimed
1889 (May 7) The Redcliffe Divisional Board was presented with a petition from the residents of the district requesting an extension to the Redcliffe Jetty. The Board agreed and appointed Messers E MacDonnell and JC Ham to make preliminary arrangements
1889 (May 29) The government nautical surveyor Mr Cullen surveyed the waters
1889 (July 15) Mr Stannix appointed as engineer for the extension project
1889 (August 6) Mr Stannix was authorised to prepare plans to extend the Jetty by 290 feet - bringing the total length to 700 feet. Tenders were called shortly after and a tender was accepted from Edward Clarke of Toowong at a cost of £588. Works were to be completed within 12 weeks. The existing diamond head was to remain and be roofed. A local hotel keeper did the plumbing required on the roof of the new pavilion and Mr Thomas Watson did the timber work, both free of charge. Work was finished December 3
1892 (January 13) JE Macgregor was appointed caretaker of the Redcliffe Jetty for £15 a year, payable monthly
1904 (February 2) A tender was accepted from E Richardson to erect gates at the entrance of the Redcliffe jetty to prevent dangerous crowding that sometimes occurred when boats came in
1906 (November 6) JE MacGregor resigned as caretaker of the Redcliffe Jetty. George Corscadden was appointed as his replacement
1917 (October 1) Plans for the construction of a sea wall were drawn up by Harding Frew and accepted by the Board. Mr Frew was appointed engineer of the project
1918 (June 10) Tenders for the sea wall construction were considered. Christie and Blondell were the successful tenderers at a cost of £3,209.13.4 for a wall 900 feet long. Another £300 covered administrative costs
1919 (July 7) The seawall at Redcliffe was officially finished
1919 (November 3) After several reports indicating that it would be more economical to build the new jetty than to repair the deteriorating old one, Mr JRW Hyde, a civil engineer, was authorised to prepare plans and specifications for a new structure. After several tests, it was decided to build the new Jetty 66 feet north of the old jetty and to extend it a further a further 200
1920 (February 2) A tender was accepted for the new Redcliffe Jetty from Taylor Bros at a cost of £14,279.17.6
1921 (July 1) Redcliffe was proclaimed a town
1921 (February 1) The Marine Department declares the old Redcliffe Jetty unsafe and it is closed to the public
1922 (January 23) The second Redcliffe Jetty officially accepted by the Redcliffe Town Council
1923 (December) The wooden Jetty pavilion was completed
1924 (November 14) The Council imposes a toll of one penny per person going onto the jetty
1925 (February 2) The toll is abolished - only to be reinstated exactly nine months later
1928 Electric power was switched on in Redcliffe
1930 The Electrical Installing Company was contracted to provide six lights on the Redcliffe Jetty
1935 The Hornibrook Highway opened
1937 The Jetty pavilion was replaced with a brick structure
1938 An entertainment parlour opened in the Halfway House on the Jetty
1959 Redcliffe was proclaimed a city
1961 Hayles Cruises Pty Ltd - the only remaining commercial boat users of the Redcliffe Jetty - produced a report on the deteriorating condition of the jetty. The results of the report meant the end of the Miramar mooring on the jetty unless the structure was repaired or replaced
1973 (December) The Halfway House demolished
1976 The Jetty was severely battered by Cyclone David
1979 The Houghton Highway opened
1983 Jetty decking was repaired
1995 The Department of Transport undertook a condition assessment and risk analysis of the jetty - recommending that the mooring and berthing of vessels be banned and a gate be installed to prevent pedestrian access during unfavourable weather
1995 (September) Redcliffe City Council calls for expressions of interest for the design and construction of a new Redcliffe Jetty. Plans went on display two years later
1998 (April) New plans that were placed on display included a breakwater facility
1998 (September 2) The Council approves the tender submitted by McMasters Queensland Pty Ltd
1998 (October) Demolition work began on the old Redcliffe Jetty
1999 (January) Construction work began on the new Redcliffe Jetty
1999 (November 27) The third Redcliffe Jetty opened
The current Redcliffe Jetty features heritage lights, seats and drinking fountains in recognition of the two previous structures. Its concrete deck also has a railway track motif along its length. Railway tracks were an important feature of the first two jetties and were used to move cargo between the head of the jetty and Redcliffe’s main street.
Hashtag your Redcliffe Jetty adventure on Insta #moretondaily or tag us @moretondaily on Facebook!
Related Stories
Top Stories
New harbour plan seeks 'middle ground'
An alternative master plan for Scarborough Harbour has been put forward aiming for the “middle ground” between campaigners and the State Government. ** FREE TO READ **
Popular Stories
Podium place for racer Kyle
Redcliffe racer Kyle Evans was back on the podium yesterday after a hard-fought second round of the Australian Formula Open (AFO). ** FREE TO READ **
New frontier opens in fire ant battle
Cutting-edge drones are taking fire-ant treatment to new heights as the national eradication program opens a depot in Caboolture. ** FREE TO READ **
Work begins at new centre
Construction has officially started on a new 150-place childcare centre and swim school in Morayfield. ** FREE TO READ **